• Renovation, Modernization, & Improvements in Safety

    In the election conducted on November 4, 2014, the community overwhelmingly supported the continued improvement of & investment in CVUSD schools by authorizing a $197M school facilities bond.

Measure I projects for each school may include:

  • Modernization, Maintenance & Repairs. Instructional Technology & Network Infrastructure. Safety & Security. Science, Mathematics & Career Preparation Labs. Project Planning & Management.

Maple Elementary - Total Measure I Bond Allocation: $2.6M

  • CAPITAL MAPLE TOTAL EXPENDITURES
      Facility Condition Assessment - School Dude $ 5,516
      Modernization General Professional Services $ 18,208
      Parking Lot Striping $ 1,259
      Kitchen Upgrade $ 15,077
      Technology Equipment Upgrades $ 67,673
      Technology Infrastructure $ 107,999
      Safety & Security $ 74,585
      Modernization $ 26,487
      Flooring $ 17,486
      Playground Equipment/ADA $ 507,289
      Program Management $ 58,123
         
    TECHNOLOGY MAPLE TOTAL EXPENDITURES
      Computers $ 58,572
      Tablets / Laptops $ 109,669
      Audio Visual $ 29,531
      Printers / Accessories $ 2,384
      Installation Services $ 6,924
      Charging Stations $ 10,101
      Miscellaneous $ 314
      Accessories $ 770